This reflects the current financial state of the project and is a very interesting figure for the payment plan.But it does not reflect how well the project is doing, as the stage of completion is not taken into consideration.The hitherto mentioned indices and percentage values can be divided into stages and represented by traffic light indicators red/yellow/green.

It can also be calculated using the Schedule Performance Index (SPI = BCWP/BCWS): An SPI of 0.8 reveals a delay whereas an SPI of 1.2 indicates a speed-up.

It clarifies the financial gap between results obtained and results planned.